As we move towards the end of the year, our Fibre to the Home areas are ramping up! 


Burgundy Estate 

Build has commenced in Springfield and the completion date for this complex is 16 October 2017.

Dates will need to be provided for La Provence, Bella Vie and Maranello.


Greater Table View

Live Zones in Phase 1: 
Zone 1.1: SDU's Live with a 4-6 week lead time
Zone 1.2: SDU's Live with a 4-6 week lead time
Zone 1.3: SDU's Live with a 4-6 week lead time

The estimated Go-Live date for zone 1.4 SDU's remains at 31 October 2017. 

Live MDU's in Table View Phase 1:
 - Villa Rustica
 - Bella Park
 - Stonebridge Park
 - Thetford Grove
 - Yorkshire Grove
 - De Oude Kaap
 - Les Chalet
 - Tuscan Villa
 - Biscanye Bay
 - Sloan Square
 - Villa Cielo

Build has commenced in Palms Resort and the completion date is 18 October 2017.

Nottingham Court and Nottinghill are still unconfirmed. Once we receive confirmation, we will communicate accordingly. 

Phase 2 (Sunningdale): We are still awaiting wayleave approval from council, as soon as we receive any updates, we will communicate accordingly. 


Tokai

Due to the delay from the City, the dates for Tokai will be changed. Once we receive the outstanding document, we will provide you with updated timelines. 


Pretoria East 

Zone 1.1  SDU's: Live with a lead time of 4-6 weeks once the order is placed. 

Chateau Lynn and Lynnwood Gardens are in progress and we estimate completing both complexes at the end of October. 

Live MDU's in Zone 1.1: 
 - Oosterberg
 - Winterberg
 - Dorphuis

Start dates for Lynnwood Hoff will be communicated once received. 

Zone 1.2 SDU's: The estimated completion date remains end of October 2017. 

Zone 1.3: Soon after 1.2 has been completed, we will be able to provide timeline estimates for this zone. 


Constantia  

Live zones with a 4 to 6 week lead time:
 - Silverhurst Estate
 - Zone 1
 - Zone 3
 - Zone 4
 - Zone 10.1
 - Zone 10.2
 - Zone 12

Please note that there several streets in Zone 1 which have high voltage lines and will require additional time for orders to be completed. This will mean that orders can take between 6 and 8 weeks to expedite. 

Streets affected: 

 - 2 to 20 Silverhurst Drive
 - Brommersvlei to Southern Cross drive
 - Silvertree Avenue
 - 1,3,5,10,13,19 Pear Lane
 - Upper Constantia Main road
 - Wycombe Road 

If you have not placed your order yet, you can Register on the Frogfoot Portal and place your order. Alternatively, you can contact your preferred internet service provider directly. 

Recent Posts

Kimberley Notification

Dear Kimberley Residents, Frogfoot is currently rolling out fibre to Kimberley to bring connect...

Frogfoot extends free fibre speed upgrades for foreseeable future

By Shane Chorley, Head of Sales and Marketing, Frogfoot NetworksFrogfoot, a licenced open-access fib...

Customer Testimonial - Gamer

Kaylen Kensley - Gamer and DevOps EngineerArea: Western CapeZone: Bergvliet 1.1Line speed: 200 MbpsD...

Customer Testimonial - Insurance Broker.

Neels Van Der Wath, Head of Short-term Insurance Brokerage at RG Brokers.          Area: Bloemfont...

Customer Testimonial - Financial Planner

Erika Lawrence - Independent Financial Planner Area: Port Elizabeth Zone: Lorraine 1.8 Line speed: 2...